How long a new roof takes, day by day

Most domestic re-roofs are shorter than people expect, but the calendar time is longer than the working time because of access and weather.

Day zero: scaffold

Access goes up before we start and is handed over tagged. This is usually a separate day and often a separate contractor.

Strip and inspect

The covering comes off a slope at a time so the roof is never fully open longer than necessary. This is the point where hidden timber problems appear and get priced.

Timber, underlay and battens

Defective rafters and battens are replaced, then breathable underlay and new treated battens go on. The roof is weathertight at this stage even before the covering returns.

Covering, ridge and details

Tiles or slates are laid, ridge and hips fitted, verges finished, and flashings renewed at chimneys, abutments and valleys.

Weather and clean-up

Wind stops work more often than rain, because open roofs and loose materials are the safety issue. We finish with a full clear-down, magnet sweep for nails, and a handover walk-round with photographs.

FAQs

What happens if it rains mid-job?

We only open what we can close, and we sheet up overnight and in bad weather. The house stays protected.

Do I need to move out?

No. A re-roof is disruptive in noise terms but the house stays habitable.

Can you work on one slope at a time?

Yes, and that's normally how we sequence it.

Related reading

More on process & paperwork and the jobs that usually come with it.

Looking for something specific? See our roofing services, cost guides, common roof problems or the areas we cover.

Get a fast quote

Family-run and Hampton-based. Tell us what you're seeing on the roof and we'll come and look properly before quoting.